The Change Partner
Hampton Bank

Project Compass | Running ledger

Action list

Draft v0.2 | 29 January 2027 | Change lead, Change Made Simple

Every action comes from a meeting or an email and links back to it. Each has one owner and a date. Detail shows the date raised and notes.

Changed in v0.2 Updated v0.2
View Showing all 28 actions.
28Actions
10Done
15Open
3Overdue
1Chased twice or more

Overdue means past its date and not done. T1 to T5 are transcripts and E2 to E4 are emails. E1, the sponsor's kick-off note, set direction and asked for no action, so it has no row here.

Closed by evidence Updated v0.2

A-09 is closed because Fatima Haddad agreed Fri 9 Apr 2027 in T5, and A-27 asks for it in writing. A-11 is closed because the criterion is on the go/no-go page with the new date.

Owner
Status
Source
ActionOwnerDueStatusSource
A-01 Confirm trainer capacity for Wave 1 and Wave 2 with the eight-person L&D team.
DetailRaised 12 Jan. Confirmed on Fri 22 Jan.
Sam PetrovicFri 22 Jan 2027DoneT1
A-02 Share the UAT script list with the Change lead.
DetailRaised 12 Jan. Shared on Fri 15 Jan.
Jorge AlvarezFri 15 Jan 2027DoneT1
A-03 Draft the stakeholder list.
DetailRaised 12 Jan. Issued at v0.1. See the stakeholder list.
Change leadFri 22 Jan 2027DoneT1
A-04 Draft the risk register.
DetailRaised 12 Jan. Issued at v0.1 with 12 risks.
Change leadFri 22 Jan 2027DoneT1
A-05 Send the Docklands shift roster pattern.
DetailRaised 14 Jan. Used for the 90-minute training blocks.
Mei TanWed 20 Jan 2027DoneT2
A-06 List the Docklands team leaders who can host 90-minute training blocks on each shift. chased once
DetailRaised 14 Jan. Chased once. Needed for A-26.
Marcus ObiWed 20 Jan 2027OverdueT2
A-07 Reply to Aroha Williams on Easter trading and log her roster limits as training constraints.
DetailRaised 13 Jan. Constraints are in the training schedule.
Change leadFri 22 Jan 2027DoneE2
A-08 Check the programme calendar against Victorian public holidays and school terms.
DetailRaised 21 Jan. Check found the school-holiday flag taken to T5.
Change leadFri 29 Jan 2027DoneE3
A-09 Confirm the Compass Assist guardrails sign-off date. Closed by evidence
DetailRaised 19 Jan. Agreed Fri 9 Apr in T5 and written into go/no-go (C-3).
Fatima HaddadFri 29 Jan 2027DoneT3
A-10 Draft an outline of the Compass Assist guardrails test set.
DetailRaised 19 Jan. Feeds step 3 of the policy timeline.
Ben OkaforFri 12 Feb 2027OpenT3
A-11 Add the Compass Assist approval gate to the go/no-go checklist. Closed by evidence
DetailRaised 19 Jan. Criterion is in go/no-go with the new date (C-3).
Change leadFri 22 Jan 2027DoneT3
A-12 Check with security the wording on customer personal data in prompts outside Salesforce.
DetailRaised 19 Jan. Policy conflict 2 on the policy timeline.
Priya RamanFri 5 Feb 2027OpenT3
A-13 Answer Q-01: which legacy CRM data comes across to Salesforce.
DetailRaised 12 Jan. Open question Q-01.
Jorge AlvarezFri 5 Feb 2027OpenT1
A-14 Supply the complaint category list, mapped to Service Cloud case categories. Due date moved
DetailRaised 14 Jan. Due date moved from Fri 29 Jan in T5. UAT depends on it.
Louise ChenFri 5 Feb 2027OpenT2
A-15 Send the month-end roster pattern for the 60 branches. chased once
DetailRaised 13 Jan. Chased once.
Aroha WilliamsWed 20 Jan 2027OverdueE2
A-16 Circulate the as-is notes for processes 1 and 4 for check.
DetailRaised 14 Jan. Checked by Tom Gallagher and Louise Chen.
Change leadFri 22 Jan 2027DoneT2
A-17 Send one banker's pipeline spreadsheet as a sample, with client details removed. chased twice
DetailRaised 15 Jan. Chased twice. Partly overtaken by A-25.
Richard VanceWed 20 Jan 2027OverdueE4
A-18 Answer Q-06: where NSW gets its Wave 2 trainers.
DetailRaised 12 Jan. Open question Q-06.
Sam PetrovicFri 12 Feb 2027OpenT1
A-19 Answer Q-03: whether branch staff are trained at their branch or on site.
DetailRaised 13 Jan. Open question Q-03.
Aroha WilliamsFri 12 Feb 2027OpenE2
A-20 Confirm the UAT environment is ready for the kick-off sessions from Mon 8 Feb.
DetailRaised 12 Jan. Go/no-go criterion.
Jorge AlvarezWed 3 Feb 2027OpenT1
A-21 Nominate the contact centre UAT testers for Docklands and Parramatta.
DetailRaised 14 Jan. Risk R-11 covers testers pulled back to day jobs.
Tom GallagherWed 3 Feb 2027OpenT2
A-22 Book steering committee slots for the go/no-go reviews before each go-live.
DetailRaised 21 Jan. Wave 1 review is before Mon 19 Apr.
Daniel NguyenFri 26 Feb 2027OpenE3
A-23 Draft the Wave 1 comms plan outline.
DetailRaised 12 Jan. Adds a bankers' message and a school-holiday reminder.
Change leadFri 12 Feb 2027OpenT1
A-24 Confirm two other business banker champions by name. New v0.2 from T4
DetailRaised 26 Jan. Richard Vance named Dev and Karina, first names only.
Isla FraserFri 5 Feb 2027OpenT4
A-25 Scope loading each banker's spreadsheet into the pipeline. New v0.2 from T4
DetailRaised 26 Jan. Two weeks of migration prep before training. Q-07 depends on it.
Anika RaoFri 12 Feb 2027OpenT4
A-26 Confirm early and late trainer blocks for Docklands. New v0.2 from T5
DetailRaised 28 Jan. Early 6:30am to 8:00am, late 4:30pm to 6:00pm.
Sam PetrovicFri 12 Feb 2027OpenT5
A-27 Confirm the guardrails test set and the sign-off date of Fri 9 Apr in writing. New v0.2 from T5
DetailRaised 28 Jan. Supports the new gate date.
Fatima HaddadFri 5 Feb 2027OpenT5
A-28 Send Helen Marchetti a one-page customer-experience scorecard outline. New v0.2 from T5
DetailRaised 28 Jan. See the KPI scorecard.
Change leadFri 19 Feb 2027OpenT5
Previous: weekly statusNext: shared facts

Sources: T1, T2, T3, T4, T5, E2, E3, E4. See also the risk register.