The Change Partner
Hampton Bank

Project Compass

Risk register

Draft v0.2 | 29 January 2027 | Change lead, Change Made Simple

Fourteen change risks: four High, seven Medium, three Low. The change plan draws on this register.

Changed in v0.2 2 updates

High risks are reported weekly in the weekly status and taken to steering by Daniel Nguyen.

Showing 14 of 14 risks. Dates are 2027.

IDRiskRatingOwnerNext stepWave
R-01Business bankers keep using personal spreadsheets after go-live. Updated v0.2
HighRichard VancePre-load pipelines, name champions, Fri 9 AprBoth
R-02Compass Assist is not approved by Risk and Compliance before go-live. Updated v0.2
HighFatima HaddadConfirm test set in writing (A-27), Fri 9 AprBoth
R-03Contact centre shift cover is short in Wave 1 training. Updated v0.2
HighTom GallagherConfirm Docklands blocks (A-26), Fri 12 FebWave 1
R-04Training capacity is limited to eight L&D staff.
MediumSam PetrovicConfirm trainer capacity, Fri 12 FebBoth
R-05Branch staff are overloaded at month end.
MediumAroha WilliamsAgree branch rosters, Fri 26 FebBoth
R-06Data migrated from the legacy CRM is of poor quality.
HighAnika RaoDecide data scope (Q-01), Fri 5 FebBoth
R-07The two-wave split creates two ways of working for a while.
MediumDaniel NguyenBrief NSW managers, Fri 30 AprBoth
R-08Complaints timers are misconfigured.
MediumLouise ChenSupply complaint categories (A-14), Fri 5 FebWave 1
R-09Sponsor attention drifts after Wave 1.
LowDaniel NguyenReview Wave 2 dates, Fri 30 AprWave 2
R-10Regional branch connectivity is unreliable.
LowPriya RamanTest the regional sites, Fri 26 MarBoth
R-11UAT testers are pulled back to their day jobs.MediumJorge AlvarezRelease named UAT testers, Mon 8 FebWave 1
R-12Ownership of Compass Assist prompt changes after go-live is unclear.MediumFatima HaddadAgree prompt-change owner (Q-02), Fri 9 AprBoth
R-13Compass Assist is off for business bankers at go-live, which delays the AI benefit for them. New v0.2LowPriya RamanOffer banker training, Fri 7 MayWave 1
R-14The guardrails sign-off moves close to go-live. New v0.2MediumFatima HaddadReview test results weekly, Fri 9 AprBoth

Assumptions

Dependencies

Change planNext: Stakeholder list

Sources: T1, T2, T3, T4, T5, E1, E2, E4.