Project Compass
Risk register
Draft v0.2 | 29 January 2027 | Change lead, Change Made Simple
Fourteen change risks: four High, seven Medium, three Low. The change plan draws on this register.
Changed in v0.2 2 updates
High risks are reported weekly in the weekly status and taken to steering by Daniel Nguyen.
Showing 14 of 14 risks. Dates are 2027.
| ID | Risk | Rating | Owner | Next step | Wave |
|---|---|---|---|---|---|
| R-01 | Business bankers keep using personal spreadsheets after go-live. Updated v0.2 | High | Richard Vance | Pre-load pipelines, name champions, Fri 9 Apr | Both |
| R-02 | Compass Assist is not approved by Risk and Compliance before go-live. Updated v0.2 | High | Fatima Haddad | Confirm test set in writing (A-27), Fri 9 Apr | Both |
| R-03 | Contact centre shift cover is short in Wave 1 training. Updated v0.2 | High | Tom Gallagher | Confirm Docklands blocks (A-26), Fri 12 Feb | Wave 1 |
| R-04 | Training capacity is limited to eight L&D staff. Likelihood/impact Medium/Medium. Eight people deliver every session in two states. Confirm capacity, ask Northgate Digital for support, settle Wave 2 trainers (Q-06). Open. T1. | Medium | Sam Petrovic | Confirm trainer capacity, Fri 12 Feb | Both |
| R-05 | Branch staff are overloaded at month end. Likelihood/impact Medium/Medium. Training spans month end and Easter trading. Agree rosters, use the week of 12 Apr block, decide where staff train (Q-03). Open. E2. | Medium | Aroha Williams | Agree branch rosters, Fri 26 Feb | Both |
| R-06 | Data migrated from the legacy CRM is of poor quality. | High | Anika Rao | Decide data scope (Q-01), Fri 5 Feb | Both |
| R-07 | The two-wave split creates two ways of working for a while. Likelihood/impact Medium/Medium. Victoria goes live seven weeks before New South Wales. Keep one process design and record lessons for Wave 2. Watching. T1. | Medium | Daniel Nguyen | Brief NSW managers, Fri 30 Apr | Both |
| R-08 | Complaints timers are misconfigured. | Medium | Louise Chen | Supply complaint categories (A-14), Fri 5 Feb | Wave 1 |
| R-09 | Sponsor attention drifts after Wave 1. | Low | Daniel Nguyen | Review Wave 2 dates, Fri 30 Apr | Wave 2 |
| R-10 | Regional branch connectivity is unreliable. Likelihood/impact Low/Medium. 20 of 60 branches are regional. Test regional sites, with a fallback to train at a nearby branch. Watching. T1. | Low | Priya Raman | Test the regional sites, Fri 26 Mar | Both |
| R-11 | UAT testers are pulled back to their day jobs. | Medium | Jorge Alvarez | Release named UAT testers, Mon 8 Feb | Wave 1 |
| R-12 | Ownership of Compass Assist prompt changes after go-live is unclear. | Medium | Fatima Haddad | Agree prompt-change owner (Q-02), Fri 9 Apr | Both |
| R-13 | Compass Assist is off for business bankers at go-live, which delays the AI benefit for them. New v0.2 | Low | Priya Raman | Offer banker training, Fri 7 May | Wave 1 |
| R-14 | The guardrails sign-off moves close to go-live. New v0.2 | Medium | Fatima Haddad | Review test results weekly, Fri 9 Apr | Both |
Assumptions
- Go-live dates hold. If not, training is rebooked.
- Guardrails are approved on Fri 9 Apr. If not, Compass Assist stays off. v0.2
- NSW school dates do not clash. TBC: confirm NSW school calendar
Dependencies
- Complaint categories from Louise Chen, due Fri 5 Feb.
- Banker spreadsheet loading scoped by Anika Rao by Fri 12 Feb (A-25). v0.2
- UAT scripts and hypercare roster from Northgate Digital.