| C-1 Stakeholder list: Richard Vance and the banker champions |
Stakeholder list Richard Vance, stance | Resistant | Conditional: he will engage if the pipeline view is better on day one. | T4 |
Stakeholder list Business banker champions | No champions listed. | Three champions added: Isla Fraser, Dev and Karina. | T4 |
| C-2 Risk register: two risks added, two changed |
Risk register R-01 mitigation | R-01 Business bankers keep using personal spreadsheets: High. The mitigation had no pipeline pre-load, no champions and no early sessions. | R-01 stays High. Mitigation: pre-load each banker's spreadsheet into the pipeline, three champions, 7:30am sessions. | T4 |
Risk register R-02 wording | R-02 Compass Assist not approved by go-live: High. Guardrails gate Fri 26 Mar 2027. | R-02 stays High. Wording now carries the new gate date, Fri 9 Apr 2027. | T5 |
Risk register R-03 rating | R-03 Contact centre shift cover during training: Medium. | R-03 Contact centre shift cover during training: High, because school holidays and Easter reduce cover. | T5 |
Risk register R-13 new | Not in the register. | R-13 Compass Assist off for bankers delays the AI benefit: Low. | T4 |
Risk register R-14 new | Not in the register. | R-14 Guardrails sign-off moves close to go-live: Medium. | T5 |
Risk register Total | 12 risks. | 14 risks. | T4, T5 |
| C-3 Go/no-go: the guardrails gate moves and two criteria are added |
Go/no-go Guardrails criterion | Compass Assist guardrails approved by Fri 26 Mar 2027. | Compass Assist guardrails approved by Fri 9 Apr 2027, 10 days before go-live. The training demo uses the approved guardrails only. | T5 |
Go/no-go New criterion | Not a criterion. | Business banker pipelines pre-loaded (at least 90 percent of bankers) by Fri 9 Apr. | T4, T5 |
Go/no-go New criterion | Not a criterion. | Complaint response drafts are labelled and editable. | T5 |
Go/no-go Criteria count | 14 criteria. | 16 criteria. | T5 |
Plan on a page, Phased rollout and Weekly status Gate date shown | Guardrails sign-off gate: Fri 26 Mar 2027. | Guardrails sign-off gate: Fri 9 Apr 2027. | T5 |
| C-4 Training and comms: built around school holidays, shifts and bankers |
Training schedule Docklands shifts | Wave 1 training in standard blocks. | Early (6:30am to 8:00am) and late (4:30pm to 6:00pm) blocks added for the Docklands shifts. | T5 |
Training schedule Branches | No school holiday handling noted. | A first block in the week of 12 Apr for people on leave in the first two weeks. | T5 |
Training schedule Make-up sessions | None. | Make-up sessions on Wed 14 Apr and Thu 15 Apr. | T5 |
Training schedule Business bankers | Half-day sessions. | 90-minute sessions at 7:30am, before client calls. | T4 |
Training schedule Compass Assist for bankers | Taught with the rest of Wave 1 and on at go-live. | Off at go-live. Taught in week 3 after go-live, as opt-in. | T4 |
| Comms plan | No bankers message and no school holiday roster reminder. | A bankers message and a school-holiday roster reminder added. | T4, T5 |
| Learning plan | Built on the v0.1 training schedule, with Q-05 unanswered. | Updated to match the training changes above and the answer to Q-05. | T4, T5 |
| C-5 Open questions: one answered and deleted, one added |
Open questions Q-05 | Open: is Compass Assist allowed to draft written complaint responses? Owner: Risk and Compliance. | Answered and deleted. Compass Assist may draft them, the complaints officer must edit and send, and drafts are labelled. The answer is now written into the solution overview (process 5), the learning plan and the changelog. | T5 |
Open questions Q-07 | Not in the register. | Q-07 added: can bankers' client notes be loaded from the spreadsheets? Owners: business banking and the CRM platform team. | T4 |
Open questions Q-04 | Open: do complaints stay in the same queue as general enquiries? | Still open. Neither transcript answers it. | No change |
Open questions Total open | 6 open: Q-01 to Q-06. | 6 open: Q-01, Q-02, Q-03, Q-04, Q-06 and Q-07. | T4, T5 |
| C-6 Action list: five added, two closed, one date moved |
Action list Totals | 23 actions: 8 done, 12 open, 3 overdue. | 28 actions: 10 done, 15 open, 3 overdue. The same three are overdue. | T4, T5 |
Action list A-09 | Open: Fatima Haddad to confirm the guardrails sign-off date. | Closed: the date is confirmed as Fri 9 Apr 2027. | T5 |
Action list A-11 | Open: Change lead adds the approval gate to the go/no-go checklist. | Closed: the gate is on the checklist. | T5 |
Action list A-14 | Louise Chen's complaint category list, due Fri 29 Jan 2027. | Same owner, due Fri 5 Feb 2027. | T5 |
| C-7 Version bump on the pages the loop touched |
Change plan, Plan on a page, Comms plan, UAT schedule, Phased rollout and Weekly status Version line | Draft v0.1, 22 January 2027. | Draft v0.2, 29 January 2027, each with a Changed in v0.2 box. | T4, T5 |
UAT schedule New dependency | No complaint category dependency. | Louise Chen's complaint categories are mapped by Fri 5 Feb, before UAT starts on Mon 8 Feb. | T5 |
| C-8 Weekly status: a new report, not an edit |
| Weekly status | Report for the week ending Fri 22 Jan 2027, v0.1. | Report for the week ending Fri 29 Jan 2027, v0.2. | T4, T5 |