Project Compass
Go / no-go checklist
Draft v0.2 | 29 January 2027 | Change lead, Change Made Simple
Wave 1 Victoria goes live on Mon 19 Apr 2027 only when all 16 criteria below are ticked. Two criteria were added in v0.2.
Changed in v0.2 Updated v0.2
- The guardrails approval criterion (3) moves from Fri 26 Mar to Fri 9 Apr 2027. From T5 (change C-3).
- Criterion 10 is new: business banker pipelines pre-loaded for at least 90 percent of bankers by Fri 9 Apr. From T4 and T5 (change C-3).
- Criterion 11 is new: complaint response drafts are labelled and editable. It records the answer to Q-05 from T5 (changes C-3 and C-5).
- The count goes from 14 criteria to 16. The gate date also appears in the phased rollout and plan on a page (change C-7).
Run 1: UAT start
Before the first kick-off session on Mon 8 Feb. Environment, access, masked data and scripts. Not shown on this page.
Run 2: Wave 1 go-live
This page. Decision meeting before go-live on Mon 19 Apr. TBC: decision meeting, proposed Fri 16 Apr
Run 3: Wave 2 go-live
The same list for Mon 7 Jun, with Parramatta 150, NSW branches 260 and NSW bankers 35 (445 people). Decision meeting proposed Fri 4 Jun.
Before go-live
| No. | Criterion | Owner | Done |
|---|---|---|---|
| 1 | Daniel Nguyen | ||
| 2 | Jorge Alvarez, Anika Rao | ||
| 3 | Updated v0.2 from T5 | Fatima Haddad | |
| 4 | Anika Rao | ||
| 5 | Jorge Alvarez | ||
| 6 | Louise Chen | ||
| 7 | Anika Rao | ||
| 8 | Priya Raman | ||
| 9 | Fatima Haddad | ||
| 10 | New in v0.2 from T5 | Richard Vance, Anika Rao | |
| 11 | New in v0.2 from T5 | Louise Chen, Fatima Haddad |
Ready for each team
Criterion 12 ticks itself when every team below has reached 90 percent in the training column. The cover column is a tracker and does not change the count.
| No. | Criterion | Owner | Done |
|---|---|---|---|
| 12 | Sam Petrovic |
| Team | People | Training at least 90 percent | Leader has confirmed cover |
|---|---|---|---|
| Contact centre, Docklands | 200 | ||
| Branch network, Victoria | 340 | ||
| Business bankers, Victoria | 45 | ||
| Complaints and advocacy | 40 | ||
| Operations | 120 | ||
| Risk and compliance | 25 | ||
| CRM platform team | 30 | ||
| L&D | 8 | ||
| Wave 1 total | 808 | ||
During go-live and hypercare
| No. | Criterion | Owner | Done |
|---|---|---|---|
| 13 | Jorge Alvarez | ||
| 14 | Tom Gallagher | ||
| 15 | Change lead | ||
| 16 | Anika Rao |
Nothing here is saved. Reload the page and every box returns to unticked. Owners are roles or named leads from the stakeholder list. Training status comes from the training schedule, and the risks behind each line are in the risk register.
Sources: T1 programme planning | T3 risk and compliance session | T4 business banking workshop | T5 steering catch-up | See also risk register, UAT schedule