The Change Partner
Hampton Bank

Project Compass

Go / no-go checklist

Draft v0.2 | 29 January 2027 | Change lead, Change Made Simple

Wave 1 Victoria goes live on Mon 19 Apr 2027 only when all 16 criteria below are ticked. Two criteria were added in v0.2.

Changed in v0.2 Updated v0.2

Run 1: UAT start

Before the first kick-off session on Mon 8 Feb. Environment, access, masked data and scripts. Not shown on this page.

Run 2: Wave 1 go-live

This page. Decision meeting before go-live on Mon 19 Apr. TBC: decision meeting, proposed Fri 16 Apr

Run 3: Wave 2 go-live

The same list for Mon 7 Jun, with Parramatta 150, NSW branches 260 and NSW bankers 35 (445 people). Decision meeting proposed Fri 4 Jun.

Trap: criterion 3 now falls on Fri 9 Apr, and the Compass Assist training demo uses the approved guardrails only. If approval slips past Fri 9 Apr, the criterion and the demo fail on the same day, with ten days left before go-live.

Before go-live

No.CriterionOwnerDone
1Daniel Nguyen
2Jorge Alvarez, Anika Rao
3 Updated v0.2 from T5Fatima Haddad
4Anika Rao
5Jorge Alvarez
6Louise Chen
7Anika Rao
8Priya Raman
9Fatima Haddad
10 New in v0.2 from T5Richard Vance, Anika Rao
11 New in v0.2 from T5Louise Chen, Fatima Haddad

Ready for each team

Criterion 12 ticks itself when every team below has reached 90 percent in the training column. The cover column is a tracker and does not change the count.

No.CriterionOwnerDone
12Sam Petrovic
TeamPeopleTraining at least 90 percentLeader has confirmed cover
Contact centre, Docklands200
Branch network, Victoria340
Business bankers, Victoria45
Complaints and advocacy40
Operations120
Risk and compliance25
CRM platform team30
L&D8
Wave 1 total808

During go-live and hypercare

No.CriterionOwnerDone
13Jorge Alvarez
14Tom Gallagher
15Change lead
16Anika Rao

Nothing here is saved. Reload the page and every box returns to unticked. Owners are roles or named leads from the stakeholder list. Training status comes from the training schedule, and the risks behind each line are in the risk register.

Sources: T1 programme planning | T3 risk and compliance session | T4 business banking workshop | T5 steering catch-up | See also risk register, UAT schedule