The Change Partner
Hampton Bank

Project Compass

Phased rollout

Draft v0.2 | 29 January 2027 | Change lead, Change Made Simple

One slide shows the four phases from UAT in February to BAU handover in June 2027, with the single gate each phase passes.

Changed in v0.2 Updated v0.2

Hampton Bank

Phased rollout

Two waves after UAT: Victoria Mon 19 Apr 2027, NSW Mon 7 Jun. The existing process stays until a team goes live.
Draft v0.2 | 29 January 2027
Change lead, Change Made Simple
FebMarAprMayJun
8152218152229512192631017243171421
School holidays and EasterHypercareHypercareGate Fri 9 Apr
Phase 1UAT
UAT 8 Feb to 12 MarSign-off 17 Mar
Phase 2Wave 1 Victoria
TrainingGo 19 Apr
Phase 3Wave 2 NSW
TrainingGo 7 Jun
Phase 4BAU handover
BAU
Phase 1UATMon 8 Feb to Wed 17 Mar 2027

Who

About 50 testers from eight teams in both states, including the banker champions.

What changes

  • Testers run scripts on masked data, with a debrief at 12:30pm daily.
  • UAT is paused on Mon 8 Mar for Labour Day.

Gate

  • No open defect rated high at sign-off.
  • Sign-off by Helen Marchetti on Wed 17 Mar.
Phase 2Updated v0.2Wave 1 VictoriaTraining Tue 30 Mar to Fri 16 Apr | Go-live Mon 19 Apr

Who

808 people: Docklands 200, branches 340, bankers 45, operations 120, complaints 40, risk 25, platform 30, L&D 8.

What changes

  • One customer view and one case in one place. Compass Assist drafts for agents and branches.
  • Bankers start with their spreadsheet pre-loaded. Compass Assist is off.

Gate

  • Guardrails approved Fri 9 Apr (was Fri 26 Mar).
  • At least 90 percent trained by Fri 16 Apr.
  • Hypercare to Fri 30 Apr.
Phase 3Wave 2 NSWTraining Mon 17 May to Fri 4 Jun | Go-live Mon 7 Jun

Who

445 people: Parramatta contact centre 150, NSW branches 260, NSW business bankers 35.

What changes

  • Same changes as Wave 1, with Parramatta training blocks set to its shift pattern.
  • The legacy CRM stays in NSW until go-live. King's Birthday, Mon 14 Jun, is in hypercare.

Gate

  • Wave 1 stable for a week after hypercare closes.
  • At least 90 percent trained by Fri 4 Jun.
  • Hypercare to Mon 21 Jun.
Phase 4BAU handoverTue 22 Jun 2027

Who

CRM platform team (30) and L&D (8) take over from the project and Northgate Digital.

What changes

  • Platform team owns configuration, roles and the pipeline.
  • Compass Assist prompt changes follow the route settled under Q-02.

Gate

  • Both hypercare periods closed.
  • Open defects and the FAQ handed over by name.

The gate for every phase

A phase goes live when its scripts pass in the live system, its guide and training are ready, its data is in, and the phase before it has been stable for a week. The 16 criteria on the go / no-go checklist all need a tick. Helen Marchetti signs on Daniel Nguyen's recommendation, and Fatima Haddad signs the Compass Assist guardrails by Fri 9 Apr Updated v0.2.

To confirm

  1. NSW school calendar and Wave 2 session dates Owner: NSW HR business partner
  2. Where NSW gets its Wave 2 trainers (Q-06) Owner: Sam Petrovic

Headcount by wave

808Wave 1 Victoria and head office: 200 Docklands, 340 branches, 45 bankers, 40 complaints, 120 operations, 25 risk, 30 platform, 8 L&D
445Wave 2 NSW: 150 Parramatta, 260 branches, 35 bankers
1,253In scope across both waves, about 1,250 people

Dates behind the slide

ItemDateNote
UAT windowMon 8 Feb to Fri 12 Mar 2027Mon 8 Mar is Labour Day in Victoria, and UAT is paused that day. Sign-off is Wed 17 Mar.
Guardrails sign-off gate Updated v0.2Fri 9 Apr 2027Moved from Fri 26 Mar so the test set can be complete. Training demos use approved guardrails only.
Victorian school holidays and EasterFri 26 Mar to Sun 11 Apr 2027Hatched on the timeline. Good Friday is Fri 26 Mar and Easter Monday is Mon 29 Mar. See Victorian school term dates and holidays and Victorian public holidays 2027.
Wave 1 training, go-live, hypercareTue 30 Mar to Fri 16 Apr; Mon 19 Apr; Mon 19 to Fri 30 AprAnzac Day falls on Sun 25 Apr, with no replacement Monday in Victoria.
Wave 2 training, go-live, hypercareMon 17 May to Fri 4 Jun; Mon 7 Jun; Mon 7 to Mon 21 JunTen working days of hypercare, because King's Birthday on Mon 14 Jun is excluded.
BAU handoverTue 22 Jun 2027The CRM platform team and L&D take over.

The timeline and the cards read from one list of phases, so they cannot disagree. The UAT schedule, go / no-go checklist and training schedule are checked against these phases first. Wave 2 is planned on the basis that the NSW school calendar shows no clash. That is to be confirmed.

Sources: T1 programme planning | T4 business banking workshop | T5 steering catch-up | E3 programme calendar | See also plan on a page, comms plan