Project Compass: change on a page
Salesforce and Compass Assist | Wave 1 Victoria, Wave 2 New South Wales | Draft v0.2, 29 January 2027
Know what changes in your day, practise it before go-live, and have someone on your floor to ask in the first two weeks.
Milestones
- Mon 8 Feb: UAT starts. Wed 17 Mar: UAT sign-off.
- Fri 26 Mar to Sun 11 Apr: school holidays and Easter.
- Tue 30 Mar: Wave 1 training starts. Fri 9 Apr: Compass Assist gate.
- Mon 19 Apr: Wave 1 go-live, Victoria.
- Mon 17 May: Wave 2 training starts. Mon 7 Jun: Wave 2 go-live, NSW.
- Tue 22 Jun: business as usual.
What changes
- Three Hamlink screens→One customer view
- Personal spreadsheets→A shared pipeline
- Emailed referrals→Referrals with an owner
- A shared mailbox→A complaint case with timers
- Typed case notes→Drafts the agent reviews
About 1,250 people in eight teams: 808 in Wave 1 and 445 in Wave 2.
The plan, team by team
- TeamWhat they hearHow they learn
- Contact centre350 peopleThe three-screen workflow is now one screen.90-minute blocks that fit the shift, with early and late blocks at Docklands.
- Branch network600 peopleReferrals live in the system, with an owner.Blocks planned around month end and Easter trading, with make-ups on 14 and 15 Apr.
- Business bankers80 peopleYour pipeline is already loaded when you log in.90 minutes at 7:30am, before client calls. Compass Assist is opt-in from week 3.
- Complaints40 peopleDrafts are labelled and yours to edit.Categories and timers mapped before UAT, then practice on masked records.
Watch
School holidays. Go-live is clear, but two of the three Wave 1 training weeks fall in the holidays and Easter. Rosters must allow for leave.
First three moves
- Pre-load every banker's pipeline and name the other two champions.
- Confirm the Docklands blocks and rosters by Fri 12 Feb.
- Get the Compass Assist test set in writing by Fri 5 Feb.